(Milford)– Construction is officially underway on the second phase of a recreational trail that will connect Dickinson County with Clay. Erin Reed of the Dickinson County Trails Board told the Board of Supervisors Tuesday crews are making good progress…
“They have started construction on phase two, the middle two miles of the Clay county connection. If you’ve been by there at all you can see that they’re really getting after it. A lot going on down there, so it’s good to see that they’re moving along.”
Reed says construction on the final one mile segment is slated for next year…
“This two miles will get us to a point where we only have one mile left next summer, so the goal is next summer, probably later next summer. We’re looking at a bidletting for that last mile in March, right now is where we’re scheduled.”
Work on the Clay county segment from the north edge of Spencer to the county line north of Fostoria is complete.